Tower Installation Update

Today (9/13) we poured concrete. Four yards (16,000 lbs.) of mud, 200 pounds of re-bar, followed by

by eight ¾” threaded rods. Everything went as planned. As we wait for the concrete to harden, we can now come up with a plan to relocate the log periodic antenna that is currently atop the Glen Martin tower that is mounted on the shipping containers.

tower-pour1
Truck setting up to pour
tower-pour2
The pour begins
tower-pour-5
The pour continues
tower-pour-6
Topping off the pour

 

tower-pour-7
Inserting threaded rods

 

tower-pour-8
Threaded rods bolted to tower template and finishing off the pour
base-4
One day later, base with forms and template removed.